PROCEDURE
Installing this industrial chiller is very simple.
The first installation of a new machine can be carried out by following these steps:
The first start of the new cooler drains the air in the water pipe, causing a slight drop in the
water level, but in order to maintain the water level in the green area, it is allowed to add
enough water again. Please observe and record the current water level, check again after
the chiller has been running for a period of time, and if the water level drops significantly,
please re-check the leakage of the water pipe.
.CHECK THE WATER LEVEL IN THE TANK.
CW-5000/5200 series uses intelligent thermostats. Usually the user does not need to adjust it. If it is really necessary.
See "Operating status and parameter tuning".
.ADJUST THE TEMPERATURE CONTROLLER PARAMETERS.
.
OPEN THE PACKAGE TO CHECK IF THE MACHINE IS FIXED AND ALL NECES-
SARY ACCESSORIES ARE COMPLETE.
.
CONNECT THE INLET AND OUTLET PIPES ACCORDING TO THE SYSTEM CONDI-
TIONS.
(1) The power switch is turned on and the circulating pump of the chiller starts to work. The first operation may
cause more bubbles in the pipe, causing occasional alarms for traffic, but after a few minutes of operation, it will
return to normal.
(2) After the first start-up, the water pipe must be checked for leakage immediately.
(3) The power supply is turned on, if the water temperature is lower than the set value, it is normal that the fan
and other parts of the machine do not work. The temperature controller will automatically control the working
state of compressor solenoid valves, fans and other components according to the set control parameters.
(4) Since the restart of the compressor and other components takes a long time, depending on different
conditions, the time varies from a few seconds to a few minutes, so do not turn off the power frequently and turn
it on again.
.
PLUG IN THE POWER SUPPLY AND TURN ON THE POWER SWITCH. (DON'T START WITHOUT WATER IN
THE TANK!)
Observe the water level gauge and add water slowly, taking care not to let the water
overflow! For the cooling of carbon steel equipment, an appropriate amount of cooling
water additive (anti-corrosion water aqua) should be added to the water. Users in cold
regions should use non-corrosive antifreeze.
.
OPEN THE WATER SUPPLY INLET TO SUPPLY COOLING WATER (DON'T SPILL