Placement
Install the energy meter after the main
switch and before the division in sub-
circuits.
Follow the manufacturer’s
instructions to install the energy
meter.
1.
Install the Primary charger according
to the Installation Guide and connect it
to the energy meter.
2.
Connect the secondary chargers
as described in the Installation section
of this manual.
3.
The Energy Meter is connected only
to the Primary Charger
4.
Connect the energy meter to the
primary charger using the lower cable
entry-apertures.
5.