5.3 Commissioning, operation
Check the sealing at the process connection over the entire scale
range before commissioning.
valves slowly.
After installation, open the vent valve (if available) or set from CLOSE
to OPEN. The version of the vent valve depends on the
model and can deviate from the illustration shown!
information on the ingress protection, see Technical information IN 00.18.
The instrument must not be subjected to any external loading (e.g.
use as a climbing aid, support for objects).
6. Faults
Personnel: Skilled personnel
CAUTION!
Physical injuries and damage to property and the
environment
If faults cannot be eliminated by means of the listed measures,
the instrument must be taken out of operation immediately.
Ensure that there is no longer any pressure present and
protect against being put into operation accidentally.
Contact the manufacturer.
If a return is needed, please follow the instructions given in
chapter 8.2 “Return”.
back page of the operating instructions.
5. Commissioning, operation / 6. Faults