Chapter 1
Introduction
This document provides hardware and soware installaon procedures for the half-height, half-
length Xilinx
®
Alveo
™
U50 data center accelerator card and applies to 2020.1.1 tools versions
and later. For installaon procedures using earlier tool versions, see v1.6 of Alveo U50 Data
Center Accelerator Card Installaon Guide (UG1370).
The Alveo U50 data center accelerator cards are PCIe
®
Gen3 x16 compliant and Gen4 x8
compable cards featuring the Xilinx 16 nm UltraScale+
™
technology. The Alveo U50 card
recommends 8 GB HBM to provide high-performance, adaptable acceleraon for memory-
bound, compute-intensive applicaons including database, analycs, and machine learning
inference.
Dierent system conguraons are available for running, developing, and debugging applicaons
on your Alveo accelerator cards:
• Running Applicaons: To congure a system to run accelerated applicaons, install an Alveo
card into a system as described in Chapter 3: Card Installaon Procedures along with the
required deployment soware to support running applicaons as described in Chapter 4:
Installing the Deployment Soware.
• Developing Applicaons: To develop FPGA accelerated applicaons, it is necessary to install
both the deployment soware and the development soware. Development soware
installaon, described in Chapter 6: Next Steps, consists of installing both a development
target plaorm and the Vis
™
environment. This conguraon does not have an Alveo card
installed and is used for development along with debugging in emulaon modes.
• Running, Developing, and Debugging Applicaons: By installing the Alveo card along with
both the deployment and development soware on a single machine, you can congure a
system for developing and running accelerated applicaons. With the card installed,
developers can debug applicaons in both emulaon modes and on the hardware.
Card Features
The Alveo U50 accelerator card features are as follows.
• UltraScale+
™
XCU50 FPGA
Chapter 1: Introduction
UG1370 (v1.7) December 9, 2020 www.xilinx.com
Alveo U50 Data Center Accelerator Card Installation Guide 6