4.
Pull AC power cables to power distribution box, Neutral should be shorted
with ground point to meet TN-S grounding system.
5.
Connect DC+/DC- 2 line wires and to 2 poles of No Fuse Breaker in DC
battery. Connect the Protective Earth wire (Green/Yellow) to ground point of
power distribution box.
6.
Turn on the power source; turn on Aux. breaker & all main NFB of EVSE then
the EVSE be ready for operational testing.