FPS/FPSE/FPD TECHNICAL TRAINING AND SERVICE WORKBOOK
VENTING INSTALLATION cant.
Exterior installation clearance requirements are crucial and must be met to ensure
compliance with all safety and code requirements. If all clearances cannot be
met, do not unpack the heater.
Exterior
Clearances:
FPD
All exterior clearance requirements for the FPO are measured from the vent
termination.
Min. clearances for side wall venting: Min. clearances for vertical:
Inside corner - 3' l' above or 4' to the side of any
Side of door or window - 9" gable, dormer, roof structure
Above door of window - 9" with building interior access.
Above public walkway - 7' l' above snow level.
Above ground or snow level -1'
Air intake to a living space - 3' above if air intake is within 10'