100 ACS2000 DFE UM 3BHS360367 ZAB E01 REV. K
Motor
Insulation tests
Power supply
1. Motor installed, aligned and alignment protocol available
2. Motor not coupled to driven load
3. Ground connection completed
4. Motor auxiliaries (bearing lubrication, heater cooling etc.) ready
1. All power cables to input transformer, between input transformer and drive, and from drive to motor mea-
sured, measured values within the required limits.
2. Report of the megger test available
If the test is carried out by the commissioning engineer of the drive, an
additional day per drive motor combination needs to be reserved.
After the test, the feeder cables can be connected, except at the drive
end. The test must comply with the specification.
1. Medium voltage available for start-up of drive
2. Low voltage auxiliary power available for start-up of drive