94 ACS2000 DFE UM 3BHS360367 ZAB E01 REV. K
7.1 Required qualification
Commissioning, parameter adjustments and functional tests of the
drive must be carried out only by commissioning personnel certified by
ABB.
7.2 Commissioning procedure
Information on the commissioning procedure and the start conditions
for commissioning can be obtained from ABB.
To contact the ABB service organization, see
Contact information
.
7.3 Commissioning check list
In order to ensure uncomplicated and speedy commissioning, it is
important that drive and associated equipment are ready for
commissioning. Reviewing and completing the items in the
Commissioning check list before the commissioning personnel arrive
on site will help to achieve this.