16 EN – Main switch and EMC C1 filter options installation supplement
EN
DA
DE
ES
FI
FR
IT
NL
PL
PT
RU
SV
TR
ZH
Installation
Do according to the R1…R5 quick installation and start-up guide of
the drive
Check if capacitors need to be reformed.
Select the power cables.
Ensure the cooling.
Protect the drive and input power cable with suitable fuses.
•R1R2:
Open the cover by removing one screw on each side.
•R3:
Open the top cover by removing two screws on each side and then the cable
box cover by removing two screws on each side.
•R4: Open the top cover by removing three screws on each side and then the
cable box cover by removing two screws on each side.
•R5:
Open the top cover by removing five screws on each side and the cable box
cover by removing two screws on each side.
Note: If the drive has a main switch (+F278 or +F316), it must be in the OFF
position (see the figure below) to be able to open the cable box cover.
Install the drive on the wall.
OFF

Table of Contents