Manual for Induction Motors and Generators
Commissioning Report - 125
3BFP 000 050 R0101 REV E
5 Electrical installation
5.1 Insulation resistance test
5.2 Accessories resistance test
Network variation:
Space heater operation:
Space heater for slip ring unit:
Stator winding (1 min., 1000 VDC): __________M
Ω, tested by________ kV, winding temperature:______ºC
Stator winding (15 / 60 s. or 1 / 10 min.): PI =__________
, tested by________ kV, winding temperature:______ºC
Rotor winding (1 min.): __________M
Ω, tested by________ kV, winding temperature:______ºC
Exciter stator (1 min., 500 VDC): __________M
Ω, tested by________ kV, winding temperature:______ºC
Space heater: __________M
Ω (500 VDC)
Temperature detectors: __________M
Ω (100 VDC)
N-end bearing insulation: __________M
Ω (100 VDC)
Stator 1 Pt 100:
Stator 2 Pt 100:
Stator 3 Pt 100:
Stator 4 Pt 100:
Stator 5 Pt 100:
Stator 6 Pt 100:
__________
Ω
__________Ω
__________Ω
__________Ω
__________Ω
__________Ω
Bearing Pt 100 D-end:
Bearing Pt 100 N-end:
__________Ω
__________Ω
Air temperature 1 Pt 100:
Air temperature 2 Pt 100:
__________Ω
__________Ω
Anti-condensation heater: __________Ω
no yes,
voltage:______-______V, frequency:_____-______Hz
no manual automatic, controlled by:_________________
no yes,
voltage:_____________V, power:_______________W