PCS100 AVC-40 Commissioning Checklist 7
Contents
About This Document ......................................................................................................................................................... 2
The Company ............................................................................................................................................................................................................ 2
Quality Control ......................................................................................................................................................................................................... 2
For More Information ............................................................................................................................................................................................. 2
Document Information ........................................................................................................................................................................................... 3
This Document ......................................................................................................................................................................................................... 3
Usage .......................................................................................................................................................................................................................... 3
Who Should Read This Document? ...................................................................................................................................................................... 3
Prerequisites ............................................................................................................................................................................................................. 3
Software Revision .................................................................................................................................................................................................... 3
Safety 4
Safety Instructions .................................................................................................................................................................................................. 4
Safety Notices .......................................................................................................................................................................................................... 6
Commissioning Checklist .................................................................................................................................................. 8
1.1 Pre-Power Visual Checks .............................................................................................................................................................................. 8
1.2 DIP Switch Settings .................................................................................................................................................................................... 10
1.3 Power Connection Checks .......................................................................................................................................................................... 12
1.4 Earth (Ground) Checks ................................................................................................................................................................................ 13
1.5 Change Frequency from 50Hz to 60Hz (if required)............................................................................................................................ 14
1.6 Initial Power Up Utility Supply ............................................................................................................................................................... 14
1.7 Stop Enable Switch Test ......................................................................................................................................................................... 16
1.8 Initial Run No Load ................................................................................................................................................................................... 16
1.9 External Transformer Wiring Check No Load ...................................................................................................................................... 17
1.10 External Transformer Thermal Test (Optional) ..................................................................................................................................... 17
1.11 Load Test ...................................................................................................................................................................................................... 18
1.12 Documentation and Handover ................................................................................................................................................................. 18
1.13 PCS100 AVC-40 Settings ........................................................................................................................................................................... 19
1.14 Deviations ..................................................................................................................................................................................................... 20
1.15 Sign-Off ......................................................................................................................................................................................................... 20