21
Mounting the terminal Chapter 5
Installing the terminal
Procedure
1. Place the two terminals next to each other on a flat surface.
2. Fasten a side-by-side mounting plate (PosNo 1).
Use four of the delivered screws.
3. Carefully turn the two terminals up-side down.
4. Fasten the second side-by-side mounting plate.
Use the remaining four screws.
5. Follow the instructions in section 2.1 to mount the mounting
angles (PosNo 5) and install the side-by-side assembly in the
rack.
2.3 Mounting in a flush or semi-flush installation
Make sure a flush or semi-flush mounting kit is available before proceeding.
The procedure for flush and semi-flush mounting is mainly the same. In semi-flush
mounts a distance frame is added. The delivered mounting seal is only necessary to ful-
fill IP 54.