Displays instances of ZMCPDIS (21).
Main menu/Test/Function status/Impedance Protection/DistanceZones(PDIS,21)/
ZMC
Displays instances of ZMCAPDIS (21).
11.6.3.4
Fullscheme distance protection, quadrilateral for earth faults ZMMPDIS,
ZMMAPDIS (21)
Main menu/Test/Function status/Impedance protection/QadEarthDistance(PDIS,
21)/ZMM
Displays the output data of ZMMPDIS (21) for zone 1.
Main menu/Test/Function status/Impedance protection/QadEarthDistance(PDIS,
21)/ZMM
Displays the output data of ZMMAPDIS (21)for zone 2-5.
11.6.3.5 Faulty phase identification with load enchroachment FMPSPDIS (21)
Main menu/Test/Function status/Impedance protection/PhaseSelection(PDIS,21)/
PHM
Includes current and voltage level settings.
11.6.3.6 Phase selection with load encroachment FDPSPDIS (21)
Main menu/Test/Function status/Impedance Protection/PhaseSelection(PDIS,21)/
PHS1
Displays one instance of FDPSPDIS (21) with a number of measurements. These
measurements show faults detected per phase as well as pickup conditions.
11.6.3.7 Phase preference logic PPLPHIZ
Main menu/Test/Function status/Impedance protection/
PhasePreferenceLogic(PDIS,21)/PPL
Displays the output data of PPLPHIZ.