Loading...
If the IEC61850-9-2LE communication is interrupted during current
injection, the report tool in PCM600 will display the current that was
injected before the interruption.
IEC10000032-1-en.vsd
IEC10000032 V1 EN
Figure 11: PCM600 report tool display after communication interruption
9.7 Testing the protection functionality
Each protection function must be tested individually by secondary injection.
Verify operating levels (trip) and timers.
Verify alarm and blocking signals.
Use the disturbance handling tool in PCM600 to evaluate that the protection
function has received the correct data and responded correctly (signaling and
timing).
Use the event viewer tool in PCM600 to check that only expected events have
occurred.