u Each time the three nuts (61037) are gradually tightened, check rotor
by turning it. The blades must not touch other parts.
CAUTION
If the blades have insufficient or no clearance between the rotor and
the casing, the blades and the casing may be damaged.
u Fit the remaining oiled nuts (61037) complete with new Verbus Ripp®
washers (61051) and tighten with pre-tightening torque (MV) (see
chapter Table of tightening torques).
u Tighten all nuts (61037) in a star pattern with tightening angle (DW)
(see chapter Table of tightening torques)
u Remove the lifting gear.
u Remove guide rod (90490).
u Screw in the speed sensor (86505) together with the O-ring (86506)
and plug in the cable connector (86515).
u Reconnect oil and air lines.
Version with compressor wheel cooling system
u Fit the air supply line. (See also chapter entitled Preliminary remarks /
Layout and functionality)