Testing for Proper Venting and Sufcient Combustion Air for Non-Direct Vent Applications
After the gas furnace has been started, the following test
should be conducted to ensure proper venting and sufcient
combustion air has been provided to the unit as well as to
other gas–red appliances which are separately vented.
If this furnace replaces a Category I furnace which was
commonly vented with another gas appliance, the size of the
existing vent pipe for that gas appliance must be checked.
Without the heat of the original furnace ue products, the
existing vent pipe is probably oversized for the single water
heater or other appliance. The vent should be checked for
proper draw with the remaining appliance.
The test should be conducted while all appliances (both in
operation and those not in operation) are connected to the
venting system being tested. If the venting system has been
installed improperly, or if provisions have not been made
for sufcient amounts of combustion air, corrections must
be made as outlined in the previous section.
1. Seal any unused openings in the venting system.
2. Visually inspect the venting system for proper size
and horizontal pitch. Determine there is no blockage
or restriction, leakage, corrosion, or other deciencies
which could cause an unsafe condition.
3. To the extent that it is practical, close all building doors
and windows and all doors between the space in which
the appliances connected to the venting system are
located and other spaces of the building.
4. Close replace dampers.
5. Turn on clothes dryers and any appliances not
connected to the venting system. Turn on any exhaust
fans, such as range hoods and bathroom exhausts, so
they will operate at maximum speed. Do not operate a
summer exhaust fan.
6. Follow the lighting instruction to place the appliance
being inspected into operation. Adjust thermostat so
appliance will operate continuously.
7. Use the ame of match or candle to test for spillage
of ue gases at the draft hood relief opening after 5
minutes of main burner operation.
8. If improper venting is observed during any of the above
tests, the venting system must be corrected or sufcient
combustion/makeup air must be provided. The venting
system should be re–sized to approach the minimum
size as determined by using the appropriate tables in
appendix G in the current standards of the National Fuel
Gas Code ANSI-Z223.1/NPFA 54 in the U.S.A., and
the appropriate Natural Gas and Propane appliances
venting sizing tables in the current standard of the
CSA-B149 Natural Gas and Propane Installation Codes
in Canada.
9. After determining that each appliance remaining
connected to the common venting system properly
vents when tested as indicated in step 3, return doors,
windows, exhaust fans, replace dampers and any other
gas burning appliance to their previous condition of use.
CARBON MONOXIDE POISONING HAZARD
Failure to follow the steps outlined below for each
appliance connected to the venting system being
placed into operation could result in carbon monoxide
poisoning or death.
The following steps shall be followed for each appliance
connected to the venting system being placed into
operation, while all other appliances connected to the
venting system are not in operation.