ARCA Regler GmbH 9 Commissioning / Decommissioning
Series 8C D / 6H D 19 / 2811.2018 / 1.0
9 Commissioning / Decommissioning
Before the initial
commissioning
In order to avoid damage to the trim due to possible existing contamina-
tion in the piping network, the piping network must be cleaned by rinsing
and if necessary pickling.
The following procedures are recommended:
Rinsing with rinsing set
A rinsing set and rinsing flange(s) is mounted in place of the trim.
Completely dismantle the valve so that only the housing remains in
the pipeline
Mount the rinsing set in place of the seat (to be ordered separately)
Mount the rinsing flange(s) (to be ordered separately)
Rinse and if necessary pickle
Dismount the rinsing set and the rinsing flange(s)
Clean the valve and replace the seal(s)
Mount the trim and completely reassemble the valve
Rinsing with spacer
A spacer is installed in the pipeline in place of the valve
Remove the valve from the pipeline (flange-mounted valves only)
Install the spacer in the pipeline
Rinse and if necessary pickle
Remove the spacer from the pipeline again
Replace the seals
Install the valve in the pipeline again
Commissioning
Pay attention to the chapter entitled [2] Safety
Avoid thermal shocks
Bring the valve slowly up to operating temperature
At a temperature difference of 300 K or more, the speed of tem-
perature change must be restricted to max. 2 K/min.
Check the flange connections for leaks
Tighten the bolted connections diagonally. Refer to the chapter
entitled [12] Torque tables for the tightening torques
Check the stem sealing for leaks
See the chapter entitled Stem seal – Detail X for this
Decommissioning
We recommend the following procedure for taking the valve out of ser-
vice:
The valve remains installed
In case of lengthy standstills, the valve and the pipeline must be emptied
and rinsed, depending on the operating medium.
The valve is removed
Pay attention to the chapter entitled [2] Safety
Remove the valve from the pipeline
Treat the interior of the housing with a suitable preservative and seal
the openings with suitable caps

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ARCA ECOTROL 8C D Series and is the answer not in the manual?

ARCA ECOTROL 8C D Series Specifications

General IconGeneral
BrandARCA
ModelECOTROL 8C D Series
CategoryControl Unit
LanguageEnglish

Related product manuals