COMMISSIONING
FIRST IGNITION OPERATION
1. Check the electrical supply.
Complete . . . . . . . . . . . . . . . . . . .
Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installer . . . . . . . . . . . . . . . . . . . . . . . . . .
2. Check the type of gas and
change the gas if necessary.
Complete . . . . . . . . . . . . . . . . . . .
3. Check the gas tightness.
Complete . . . . . . . . . . . . . . . . . . .
4. Measure the gas inlet
standing pressure
Complete ..........................................................................................
5. Check the Flue
Complete . . . . . . . . . . . . . . . . . . .
6. Fill the installation.
Complete . . . . . . . . . . . . . . . . . . .
7. Check the hydraulic water
tightness.
Complete . . . . . . . . . . . . . . . . . . .
8. Set the heating power.
Complete . . . . . . . . . . . . . . . . . . .
9. Balance the central heating
circuit.
Complete . . . . . . . . . . . . . . . . . . .
10. Measure the gas inlet
working pressure.
Complete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
11. Check the boiler
combustion.
Complete . . . . . . . . . . . . . . . . . . .
12. Gas rate the appliance.
Complete . . . . . . . . . . . . . . . . . . .
13. Explain to the end user
how to use the boiler/
timer/control
Complete ..........................................................................................
14.Complete the Benchmark
Log Book
Complete . . . . . . . . . . . . . . . . . . .