29
commissioning
FIRST IGNITION OPERATION
1. Check the electrical supply.
Complete . . . . . . . . . . . . . . . . . . .
Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installer . . . . . . . . . . . . . . . . . . . . . . . . . .
2. Check the type of gas and
change the gas if necessary.
Complete . . . . . . . . . . . . . . . . . . .
3. Check the gas tightness.
Complete . . . . . . . . . . . . . . . . . . .
4. Measure the gas inlet/
standing pressure
Complete . . . . . . . . . . . . . . . . . . .
5. Check the ue installation.
(See Connecting the ue)
Complete . . . . . . . . . . . . . . . . . . .
6. Fill the installation and
ush. See page 28
Complete . . . . . . . . . . . . . . . . . . .
7. Check the hydraulic water
tightness.
Complete . . . . . . . . . . . . . . . . . . .
8. Spin the pump.
Complete . . . . . . . . . . . . . . . . . . .
9. Purge air by pressing ESC
button for 5 sec. & manually
vent the exchanger
Complete . . . . . . . . . . . . . . . . . . .
10. Change the language in
the display (if necessary).
Page 33.
Complete . . . . . . . . . . . . . . . . . . .
11. Set the hour, and the date.
See page 33
Complete . . . . . . . . . . . . . . . . . . .
12. Set the heating power. See
page 33
Complete . . . . . . . . . . . . . . . . . . .
13. Balance the central
heating circuit.
Complete . . . . . . . . . . . . . . . . . . .
14. Measure the gas inlet
working pressure.
Complete . . . . . . . . . . . . . . . . . . .
15. Check the combustion
rate. See page 34
Complete . . . . . . . . . . . . . . . . . . .
16. Gas rate the appliance
Complete . . . . . . . . . . . . . . . . . . .
17. Explain to the end user the
working of the boiler and
controls
Complete . . . . . . . . . . . . . . . . . . .