1. Commissioning
1.1. Filling of the tank
Open one or several hot water taps.
Open the cold water tap on the security group (make sure that the drain valve is closed).
When water starts flowing from the hot water taps close them. The tank is full.
Check the connections for possible leaks.
Check the correct function of valves and safety group by opening them several times in order to eliminate
possible particles.
Overview Installation Operation Maintenance Warranty
Operation
10.2. First operation
If the water heater has been tilted wait for minimum 1h before operation.
Check the information
Follow the instructions
Access to mode
and settings
Navigate
Increase the values
Return to previous screen
Confirm
Navigate
Reduce the values
Increase of hot water
production
2. Description of pictograms.
Consigne eau chaude
Absence registered / in operation
Anti-legionella heating cycle
Electric backup working
Heat pump working
Fast heating confirmed