bracket (see Figure below) and all required fasteners and must be order separately (Order
Code AL351
1003–E6).
Rack requirements:
•
provide the equivalent of one rack of vertical space for each switch in an E1A or 1EC
standard 19 inch (48.2 cm) equipment rack and T1A 23 inch (58.5 cm) equipment rack.
• appropriate rack space to accommodate 1U switch height (44 mm).
• rack bolted to floor and braced if necessary
• rack must be grounded to the same grounding electrode used by the power service in the
area. The group path must be permanent and must not exceed 1 Ohm of resistance from
the rack to the grounding electrode.
Perform the following procedure to install your switch in a equipment rack.
Procedure
1. Ensure power is disconnected from the switch.
2. With the front of the ERS 3510GT or ERS 3510GT-PWR+ unit facing you, attach
the small bracket from the optional kit to the right side of the switch using the flathead
screws provided.
3. With the front of the ERS 3510GT or ERS 3510GT-PWR+ unit facing you, attach
the long bracket from the optional kit (see Figure that follows) to the left side of the
switch using the flathead screws provided.
Installation preparation
February 2013 11