Operation manual for BAUER RAINSTAR Series T32, T42 14
6 PUTTING INTO OPERATION
ASSEMBLY INSTRUCTIONS
In order to provide optimum conditions for transport and time-saving assembly, all components are directly
mounted or fixed on the machine.
The shipment contains no loose or separate parts.
Please assemble the RAINSTAR according to the following instruction before the initial start-up. This takes about
two hours.
PERFORM ALL STEPS WITH UTMOST CARE IN ORDER TO
AVOID ACCIDENTS AND INJURIES.
If you use a truck mounted crane to unload the RAINSTAR, please proceed as follows
1.1. Pick up the machine with the crane hook.
Lower it in horizontal position to about 0.5 m above the ground
1.2. Mount the RAINSTAR wheels. The threaded hole on the axle (for indication bolt) must point towards the
setting slot.
1.3. Set the desired RAINSTAR track width and fix it.
Track width indication (point 3),
securing (points 1+ 2).
1.4. Fix the axle with bolts 1+2
1.5. Mount the jack.
1.6. Park the RAINSTAR on the ground on its wheels and on the jack