LR-10000 Low-Rise Scissor Lift 9 P/N 5900075Rev. B August 2021
Installation Checklist
Following are the steps needed to install your LR-10000 Lift. Perform them in the order shown.
1. Review the installation Safety Rules.
2. Plan for Electrical Work.
3. Make sure you have the necessary Tools.
4. Select the Installation Site.
5. Make sure there is adequate Clearance on all sides of the Lift.
6. Select the Power Unit Stand location.
7. Create Chalk Line Guides.
8. Anchor the Bases.
9. Install the Safety Lock Release Handle.
10. Anchor the Power Unit Stand and Attach the Power Unit.
11. Learn about Hydraulic Fluid Contamination.
12. Learn about Liquid Thread Sealant.
13. Connect the Hydraulic Hoses.
14. Prepare the Power Unit (
Electrician required
).
15. Install a Power Disconnect Switch and Thermal Disconnect Switch (
Electrician required
).
16. Review the Final Checklist.
17. Leave the Manual for the owner/operator.
18. Perform an Operational Test.