SP-7XE/F Full-Rise Scissor Lift 29 P/N 5900010Rev. B3 — September 2023
6. Wrench each Nut clockwise to the recommended installation torque, 85 95 ft-lbs. using a
Torque Wrench.
Important: Do not use an impact wrench to torque the
Anchor Bolts.
Wrenching the Nut forces the Wedge up, pushing out the
Expansion Sleeve and pressing it tightly against the
Concrete.
Grouting the Lift Bases
If no shims were used, there is no requirement to grout the Bases of the Lift. Using Shims to level the
Lift Platforms will create a void between the Lift Base and the existing concrete. These voids must be
filled to support the downward force exerted by the Slide Blocks as they travel along the base. Tuck
point a non-shrinking structural grout or cement to fill the voids and provide this support. A variety of
structural grouts and cements are available: Quikrete® Fast Set® non-shrink grout is one such option.
Allow the material to cure to the manufacturer’s specifications before applying
weight to the Lift.