Transport, Installation and Connection
4-4
4.7 Installation
All installation and connection work may be carried out by
qualified and approved specialist staff only ! The legal
regulations as well as adjustment instructions of the plant
operator have to be observed!
1 Compact Flame Controller
2 Heating insulator
3 Swivel mount
The sighting tube connection has a G1" internal pipe
thread.
In order to ensure perfect flame monitoring, the correct
and low-vibration position of the sighting tube relative to
the flame is a significant pre-requisite. For selective
burner monitoring, the device has to be installed in such a
way that the primary combustion zone in all load ranges is
inside the visual angle of the compact flame controller.
The sighting axis must, if possible, intersect the first third
of the flame of the own burner. The extension of the sight-
ing axis must not intersect the first third of the flame of
other burners. Adjust the compact flame controller so that
an optimum sighting is obtained.