TECHNICAL INSPECTIONS
To make sure your S2000-2 controller keeps proper operability it must be inspected by a competent
specialist at least on receipt and annually. The inspection algorithm shall include:
Visual checking S2000-2 for contaminations and mechanical damage
Verifying S2000-2 for secure mounting and wire connection conditions
Inspection of S2000-2 operability in accordance with the techniques shown below
The S2000-2 controller must be tested under the following ambient conditions:
Temperature 25° ± 10°C
Relative humidity 45 ÷ 80 %
Atmospheric pressure 630 ÷ 800 mm Hg
WARNING! Disconnect the S2000-2 controller power supply before wiring and
unwiring the device while testing
NOTE: Technical readiness period of the S2000-2 does not exceed 5s
The wiring diagram for the controller operability inspection is shown in Figure 18.
S2000-2 Operability Inspection
Inspect the controller operability by doing the following:
1. Remove the controller cover and power the controller on.
2. Ensure the controller makes a sound
3. Measure the consumed current value; it must not exceed 120mA.
4. Ensure the network controller displays the event of controller being found.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the bolid S2000-2 and is the answer not in the manual?

bolid S2000-2 Specifications

General IconGeneral
Brandbolid
ModelS2000-2
CategoryController
LanguageEnglish