Pre-Installation
Greenstar Danesmoor Utility
ErP+
and Utility System
ErP+
- 6 720 821 720 (2018/04)14
4.4 Water systems and pipework
Primary system plastic pipework:
• Any plastic pipework used for the CH system must have a polymeric
barrier, complying with BS 7921 and installed to BS 5955 with
1000mm (minimum) length of copper or steel pipe connected to the
boiler.
• Plastic pipework used for underfloor heating must be correctly
controlled with a thermostatic blending valve limiting the
temperature of the circuits to approximately 50°C with 1000mm
(minimum) length of copper or steel pipe connected to the boiler,
and a 20K differential must be maintained at the appliance.
Primary system/connections/valves:
• Do not use galvanised pipes or radiators.
• All system connections, taps and mixing valves must be capable of
sustaining a pressure of 3 bar.
• Radiator valves should conform to BS 2767:10.
• All other valves should conform to BS 1010.
• An automatic bypass valve must be connected between the heating
flow and return where TRVs are used on all radiators, fitted to give at
least a 3 metre circuit when activated.
• Drain cocks are required at all the lowest points on the system.
• Air vents are required at all high points on the system.
Open vent primary system (Regular only)
• The open vent pipe (F) and feed and expansion pipe (H) must rise
continuously from the appliance.
• The feed and expansion cistern (E) must be positioned to provide a
static head (S) of at least 1 metre above the highest point in the
heating system to the water level in the feed and expansion cistern.
• Ensure adequate space is left in the expansion cistern for expansion
of the system water.
• No valve shall be fitted in the open vent pipe (F) or the feed and
expansion pipe (H).
• The open vent pipe (F) must be at least 22mmØ.
Fig. 11 Regular boiler, open vent layout
[A] Regular appliance
[A1] System appliance
[B] Expansion vessel*
[C] Automatic bypass valve
[D] Drain cock
[E] Feed and expansion cistern
[F] Open vent 22mmØ min.
[G] Pressure gauge*
[H] Feed and expansion 15mmØ min.
[J] Circulating pump*
[K] Zone valves
[K1] Three port valve
[L] Lockshield valve
[M] Hot water cylinder
[N] Automatic air vent
[P] Pressure relief valve*
[P1] Pressure relief discharge*
[R] Radiators
[T] Thermostatic radiator valve TRV
[U] To filling system
[NOTE] * Components included in the System boiler
NOTICE:
▶ The boiler should not be allowed to operate with a
return temperature of less than 30°C when the
system is up to operating temperature.