MAINTENANCE MANUAL LINE
TIME LIMIT FOR PARTS
General note
NOTICE
This time limit must be followed independently and in addition to the visual in-
spections (see Chapter 05-20-00 section: Visual Inspection) of the respective
components.
Time limit The following components and systems must be replaced every 5 years:
All rubber hoses of the cooling system (except GENUINE ROTAX® silicon hoses),
which need to be checked by “on-condition” maintenance according to the instructions
of continued airworthiness.
All rubber hoses of the lubrication system which are part of the engine supply volume
and if they are not in the maintenance schedule of aircraft manufacturer
Connecting hose of the air intake system
V-belt for optional external alternator
Fuel pressure regulator assy. (only pressure regulator, not pressure regulator housing)
Air intake hose (connection between turbocharger and airbox)
TIME LIMIT FOR THE COOLANT
General note Coolant must be replaced as per manufacturers instructions, at the latest during overhaul
or when the engine is replaced.
ANNUAL INSPECTION
General note A 100 hr. inspection is to be carried out after every 100 hours of operation or every 12
months, whichever comes first.
See Chapter 05-20-00 section Scheduled maintenance checks.
05–10–00
Page 6
December 01 2023
Effectivity: 916 i A / C24
Edition 0/Rev. 1

Other manuals for BRP ROTAX 916 i A Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the BRP ROTAX 916 i A Series and is the answer not in the manual?

BRP ROTAX 916 i A Series Specifications

General IconGeneral
BrandBRP
ModelROTAX 916 i A Series
CategoryEngine
LanguageEnglish

Related product manuals