INSTALLATION START-UP REQUEST CHECKLIST
Machine Model Number: 19DV Serial Number:
The following information provides the status of the chiller installation.
YES/NO DATE TO BE
(N/A) COMPLETED
1. The machine is level.
2. The machine components are installed and connected in
accordance with the installation instructions.
3. The isolation package and grouting (if necessary)
are installed.
4. The relief devices are piped to the atmosphere.
5. All piping is installed and supported. Direction of flow is indicated
in accordance with the installation instructions and job prints.
a. Chilled water piping
b. Condenser water piping
c. Waterbox drain piping
d. Pumpout unit piping (if installed)
e. VFD drain piping
f. Other
6. Gages are installed as called for on the job prints required
to establish design flow for the evaporator and condenser.
a. Water pressure gages IN and OUT
b. Water temperature gages IN and OUT
7. The machine’s wiring is complete. The wiring is
installed per installation instructions and certified prints.
a. Power wiring to VFD line side completed.
(If chiller was disassembled during installation, motor
leads must not be taped until the Carrier technician
megger tests the motor.)
b. Carrier controls can independently energize water pumps
and tower fan
a. The transformer feeding the VFD is confirmed to have a
Wye secondary with a solidly grounded Neutral.
Immediately contact Carrier Service if this is not the case.
b. Line side voltage is within ±10% of chiller nameplate voltage
c. Other
8. Was the chiller disassembled/reassembled during the installation?
Was this work supervised by a Carrier Service Representative?
COMMENTS:
NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices and adhere to
the safety considerations/information as outlined in preceding sec-
tions of this Installation Instructions document.
To:
Attn:
Date
Project Name
Carrier Sales Order Number