Installation Procedures
The standard attached accessories of the units of this series refer to the packing; prepare other accessories
according to the requirements of the local installation point of our company.
1. Before installation [before nishing the installation, do not dispose o󰀨 the parts included and required for the
installation]
Determine the route to move the unit to the installation site;
Do not tear the package open before moving the unit to the installation site. When unpacking is needed, a soft
material or protector block with ropes can be used to lift the unit to avoid damaging or scraping of the unit.
2. Select the installation site
(1) The installation site should be selected according to the following criterion, which should be approved by
users.
Ideal air distribution ensured; where there is no blockage in the air passage;
where the condensed water can be drained out properly;
where the location can structurally bear the weight of the indoor unit;
where enough space can be ensured for maintenance.
where the lengths of the piping between indoor units and outdoor units are within the allowable range (refer to
Installation of Outdoor Units)
where the distance of at least 1m between indoor units, outdoor units, mains supply, connecting wires and
television or radio can be maintained so as to avoid the image disturbance and noises of the above electrical
appliances. (Even if 1m can be ensured, noise might occur if there is strong electric wave.) Additionally,
equipment, television or other valuables can’t be put under the unit so as to avoid the condensed water from the
unit from dropping on the above articles, causing damages.
(2) Height of Ceiling:
The ceiling should be located at a place, where the central
position of air outlet port is less than 3m high above the ground.
(3)Hanger bolts should be used during installation. Check if
the location can bear the weight of the unit. Reinforce it before
installation if necessary.
(4) The dimensions for maintenance
Make sure that it is easy to dismount the electrical control box,
fan, motor, lter.
checking
port
barrier
space needed for installation (unit:mm)
(location of hanging bolt)
(dimensions of inspection hole on ceiling)
(location of hanging bolt)
checking
port
(dimensions of inspection hole on ceiling)
D
D
C
A
B
B
Size
Model
A
(mm)
B
(mm)
C
(mm)
D
(mm)
40VD007-018H
-7S-QEE
786 1100 472 635
40VD024-030H
-7S-QEE
986 1300 472 635
40VD038-054H
-7S-QEE
1404 1720 530 738
6
ENGLISH
> 600
> 100