EasyManua.ls Logo

CertainTeed Bufftech - Semi-Private Columbia Fence Installation; Columbia Fence: Getting Started; Columbia Fence: Digging Holes; Columbia Fence: Installing First Post

Default Icon
60 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
16
Semi-Private Fence – Columbia
1. Getting Started
• Be sure to call underground (811) prior to digging
• Assemble gates (if necessary) and decide where they will
be located
• Stake out the fence line
• Space and mark post hole locations for gate and sections
(spacer bar/template may be useful)
• Start at gate end post and work outward to determine
proper fence height relative to ground
2. Dig Holes
• Dig holes 30" deep or to frost line
- Hole size for 5 x 5 posts = approximately 12"
• Clean holes and check for straight walls
• Bell bottom of holes
3. Install First Post
• Insert post in hole
• Determine rough height
• Fill hole around post with concrete mix (sand, gravel and
cement) approximately 2" or 4" below grade
• Tamp concrete in hole to eliminate air pockets
• Level and square post
4. Install Bottom Rail
• Tape the ends of any rail going into a post that is to be filled
with concrete to prevent concrete seepage
• Depress bullet clip and insert bottom rail in post; clip will drop
down to hold rail in post
5. Install Second Post
• Insert second post in hole
• Insert bottom rail in post
• Insert block under bottom rail to position at correct
fence height
• Fill hole around second post with concrete mix
• Tamp, level and square fence
• Assembly may be continued by installing all bottom rails first,
or one section at a time
6. Support and Secure
• Level and square fence
• To lower a post, place a wood block from corner to corner on
the post and carefully tap with a mallet
• Never strike the PVC post without a wood support
7. Install Mid-Rail
• Insert mid-rail in first post with larger routed holes facing in
the down position
• Insert into second post (Note: This rail floats in post.
No bullet clips are required)
8. Install Pickets and Top Rail
• Insert all pickets through mid-rail into bottom rail
• Temporarily remove mid-rail ends from post and pull the
section forward
• Insert the top rail over the pickets starting at one end
• Insert the mid-rail and the top rail back into the posts
• Secure top rail inside post with a #8 x 3/4" screw
9. Hang Gate/Install Hardware
• For complete details, see gate installation instructions in
hardware box
• Position gate between posts
• Allow 1" gap for the hinge and 3/4" for latch and gate swing
• Block up gate to square with fence; rails should be level
• Gate hardware must be secured to two sides of the post
10. Solidify Gate Posts
• It is critical that gate hinge and latch posts are solid to ensure
proper gate functionality. Two methods are available:
A. Aluminum gate post stiffener
- Slide aluminum gate stiffener inside hinge,
latch or end posts with open end facing routed hole
- Drive a screw through the vinyl into the aluminum
stiffener at the bottom of the post
- Insert post into the ground
- Fill hole with concrete around outside of post
B. Concrete and rebar*
- Use two pieces of 1/2" rebar in each hinge, latch and
end post
- Rebar should extend from the bottom of the hole to
approximately 12" from the top of the post
- Hold rebar in opposite corners of post with rebar
separator clips
- Fill post with concrete mix to cover rebar and
hardware fasteners
- Tamp post with a rubber mallet to eliminate air pockets
- Leave gate on blocks for 72 hours to allow concrete to set
11. Install Caps
• Install post caps
• Caps may be secured with glue, silicone adhesive or
#8 x 3/4" screws, caps and washers
* Caution – In climates that experience freeze-thaw cycles, this installation method could result in post cracking over time. This would not be covered by the warranty.

Other manuals for CertainTeed Bufftech