1-24
Cisco ONS 15454 Procedure Guide, Release 8.5.1
78-18537-01
Chapter 1 Install the Shelf and Backplane Cable
NTP- A11 Install the Rear Cover
Note As needed, attach additional standoffs to the extended standoffs to meet site-specific cable 
management requirements.
Step 3 Locate the mounting holes where you will install the standoffs on the EIAs you are using. Figure 1-8 
shows the mounting holes on the UBIC-V. Figure 1-9 shows the mounting holes on the UBIC-H. 
Figure 1-10 shows the mounting holes on the remaining EIA types (MiniBNC, SMB, etc.). You can 
identify the mounting holes on all EIAs by locating the REAR COVER BRACKET LOCATION 
designation.
Table 1-4 Standoffs Required for EIA Types
EIA Type
Required Standoffs for 
One Extended Standoff
Total Required 
Standoffs per Shelf
UBIC-V One 1 3/8-inch
Two 2-inch
Four 1 3/8-inch
Eight 2-inch
UBIC-H One 1 3/8-inch
One 2-inch
Four 1 3/8-inch
Four 2-inch
MiniBNC One 1 3/8-inch
One 2-inch
Four 1 3/8-inch
Four 2-inch
BNC One 1 3/8-inch
One 1-inch
Four 1 3/8-inch
Four 1-inch
High-Density BNC
SMB
AMP Champ