Electrical connection and start-up
Recommended: install a line circuit breaker and a earth fault breaker to the
machine.
IMPORTANT!
Connect the plug to a separate earthed wall socket (230 VAC 10 A).
INSTALLATION AND START-UP
Switch
Turn on the switch located at the rear of the machine, the machine will start
filling with water.
While machine is heating up, display is blinking.
Once the water has reached the correct temperature, display will stop
blinking and show a steady light (A).
Machine is now ready to use.
A
SINGLE CATER
CATER
The brewer is not reconnectable and may only be installed to the electric
supply network with a voltage that is stated on the brewer and shall be carried
out by an authorized electrician.
Recommended: install a line circuit breaker and a earth fault breaker to the
machine.
CAUTION!
Connection to a separate 3 phase only
- Brewer should be connected to 400V with zero and earth.
- Use 10 Amp fuses.
IMPORTANT!
Electrical installations must be done of an certificated electrician: 400V 2N/