6
Installation
Model W H D
POV-44 44 3/8” 25 1/4” 12”
POV-56 56 3/8” 25 1/4” 12”
POV-68 68 3/8” 25 1/4” 12”
POV-80 80 3/8” 25 1/4” 12”
POV-96 96 3/8” 25 1/4” 12”
1. Prepare the framed opening according to the chart
above. Provide an electrical outlet on the back side of
the framed opening, near the top right corner.
2. Install L Metal Nailing Flanges.
3. Install the re unit in the framed opening with a
minimum 1 ¼ drywall screws to secure the unit.
4. Mask the exposed re unit during the drywall
process. Install drywall to the drywall stops on the
perimeter of the re box. For more information on
the drywall stops see the Product Guide on page 4.
Decorate as desired.
5. Install the side and front glass pieces.
3-Sided Installation