MODEL AGZ CHILLERS 104 www.DaikinApplied.com
WarranTy regIsTraTIon form (sCroll)
WarranTy regIsTraTIon form (sCroll)
6/12/15 MLP
Control # - SF99007
1
Attention: Warranty Department
Scroll Compressor Equipment Warranty Registration Form
Daikin
This form must be completely filled out and returned to the
P.O Box 2510
Staunton Warranty Department within ten (10) days of start-up in order to comply
Staunton, VA 24402-2510
with the terms of "Daikin Limited Product Warranty".
Email Address: STN.Wty_Startup_Registration@daikinapplied.com
Job Name: Startup Date:
Daikin G.O. No.: Daikin S.O. No.:
Installation Address: City/State/Zip:
Purchasing Contractor: Phone:
City/State/Zip: No. of units at site:
Unit Model No.:
Serial No.:
Compressor # 1 Serial #: Compressor # 4 Serial No.:
Compressor # 2 Serial. #: Compressor # 5 Serial No.:
Compressor # 3 Serial #: Compressor # 6 Serial No.:
Benshaw/DRC Control Box M/M #: Benshaw/DRC Control Box S/N #:
I. PRE START-UP PROCEDURE
II. Pre Start-Up Checklist
Pre Start-Up Checklist, All NO checks require an explanation under "Description". Please check yes or no.
YES NO
A. Is the unit free of visible shipping damage, corrosion or paint problems?
B. Is unit installed level?
C. Does the unit meet all location, installation and service clearances per IM Bulletin?
D. Has sensor bulb been properly installed in the well?
E. Are all set screws on all fans tight?
F. Does electrical service correspond to unit nameplate?
Nameplate: Volts Hertz Phase
G. Has electrical service been checked for proper phasing at each circuit power terminal block?
H. Has unit been properly grounded?
I. Has a fused disconnect and fuses or breaker been sized per product manual and installed per local code?
Number of conduits Number of Wires Wire Size
J. Are all electrical power connections tight?
K.
been operating for 24 hours prior to start-up?
Check, Test and Commissioning for
Scroll Product (AGZ, ACZ, WGZ, TGZ)