5 Installation
Installation and operation manual
12
REYQ8~20+REMQ5T7Y1B
VRV IV system air conditioner
4P353996-1E – 2018.04
5.3.2 To connect the refrigerant piping to the
outdoor unit
NOTICE
Be sure to use the supplied accessory pipes when
carrying out piping work in the field.
Be sure that the field installed piping does not touch
other pipes, the bottom panel or side panel. Especially
for the bottom and side connection, be sure to protect
the piping with suitable insulation, to prevent it from
coming into contact with the casing.
Connect the stop valves to the field piping using the accessory pipes
supplied with the unit.
The connections to the branch kits are the responsibility of the
installer (field piping).
5.3.3 To connect the multi connection piping kit
NOTICE
Improper installation may lead to malfunction of the
outdoor unit.
Install the joints horizontally, so that the caution label (a) attached
to the joint comes to the top.
Do not tilt the joint more than 7.5° (see view A).
Do not install the joint vertically (see view B).
a
a
A B
7.5°
7.5°
a Caution label
X Not allowed
O Allowed
Make sure that the total length of the piping connected to the joint
is absolute straight for more than 500mm. Only if a straight field
piping of more than 120mm is connected, more than 500mm of
straight section can be ensured.
>120 mm
>500 mm
5.3.4 Multiple outdoor units: Knockout holes
Connection Description
Front connection Remove the front plate knockout holes to
connect.
Connection Description
Bottom connection Remove the knockout holes on the bottom
frame and route the piping under the bottom.
5.3.5 To protect against contamination
Seal the piping and wiring intake holes using sealing material (field
supply), otherwise the capacity of the unit will drop and small
animals may enter the machine.
5.3.6 Using the stop valve and service port
To handle the stop valve
Make sure to keep all stop valves open during operation.
The stop valve is factory closed.
To open the stop valve
1 Remove the stop valve cover.
2 Insert a hexagon wrench into the stop valve and turn the stop
valve counterclockwise.
3 When the stop valve cannot be turned any further, stop turning.
Result: The valve is now open.
To fully open the Ø19.1 mm~Ø25.4 mm stop valve, turn the
hexagonal wrench until a torque between 27 and 33 N•m is
achieved.
Inadequate torque may cause leakage of refrigerant and breakage of
the stop valve cap.
1
2
3
4
NOTICE
Pay attention that mentioned torque range is applicable for
opening Ø19.1~Ø25.4mm stop valves only.
To close the stop valve
1 Remove the stop valve cover.
2 Insert a hexagon wrench into the stop valve and turn the stop
valve clockwise.
3 When the stop valve cannot be turned any further, stop turning.
Result: The valve is now closed.
Closing direction:

Table of Contents