www.DaikinApplied.com 59 IOM 1207-6 • TRAILBLAZER
®
MODEL AGZ CHILLERS

Figure 60: Spring Isolator
Figure 61: Rubber-in-Shear (RIS) Isolator
In all cases, set the unit in place and level. If antiskid pads are
used, do not use hold down bolts. If hold down bolts are used,
do not use anti-skid pads.
When spring isolators are required, install springs running
under the main unit supports. Unit should be installed on
blocks or shims at the listed free height. Isolator springs should
not be loaded until the installation is complete, then adjust the
springs to the vendor listed compression for the load point.
When securing the isolator, do not over-tighten the mounting
bolts. Over-tightening may result in cracking of the cast isolator
housing and will have a negative impact on the isolation e󰀨ect.
Installation of spring isolators requires exible piping
connections and at least three feet of exible electrical conduit
to avoid straining the piping and transmitting vibration and
noise.
Mounting locations for each model can be found on the
dimensional drawings starting on page 31 for units with
remote evaporators and page 45 for pump package units.
Neoprene wa󰀪e pads, supplied by customers, should be
mounted at the dened mounting point locations along the full
rail length.
Contact a Daikin Applied sales representative for isolator
information related to units with other n materials.
9.25 [235.0]
10.5 [266.7]
.56 [14.3]
7.75 [196.9]
3
[76.2]
.62 [15.8]
6.2
5
[127.0]
FREE HT.
5\X [127.0]
OPER. HT.
.5 [12.7] DIA.
POSITIONING
PIN
.25 [6.4]
ELASTOMERIC PAD
ADJ. BOLT
ELASTOMERIC
SNUBBER
.625
[15.9]
.25 TO .5 GAP
[6.4 to 12.7]