INSTALLATION
Eaton BladeUPS Bar Installation Guide S 164201723 Rev 2 www.eaton.com/powerquality
22
NOTE Loosening the mounting brackets slightly may allow easier alignment to the vertical
rail of the rack. Retighten the mounting brackets when alignment is complete.
18. Using two M6 12 hex bolts, secure the left side of the wireway
terminal block housing to the rack. See Figure 17. Torque the bolts
to 5.1 ± 0.8 Nm (45 ± 7 lb in).
19. Using six M4
8 pan-head screws, secure the wireway terminal
block housing to the wireway and to the bar. See Figure 17. Torque
the screws to 1.7 ± 0.2 Nm (15 ± 2 lb in).
M6 12 Hex Bolts
(2 places)
M4 8 Pan-Head Screws
(6 places)
Wireway Terminal
Block Housing
Rear of Rack
Front of Rack
Figure 17. Wireway Terminal Block Housing Installation