Page 26 Effective: April 2004
ATC-300 Automatic
Transfer Switch
Controller
Utility - Generator Transfer Switch
Source 1 is available
Close Source 1
(Energize K1)
Source 1 is powering the load
Source 1 becomes unavailable
(or Engine Test, Plant Exercise, Go To Emergency)
TDES timer times out
Send "Engine Start" signal
(Energize Gen Start relay)
Is Source 2
Available?
TDNE timer times out
Open Source 1
(Energize K2)
TDN timer times out
(If Option 32A is enabled)
Close Source 2
(Energize K2)
Source 2 is powering the load
Is Source 1
Available?
TDEN timer times out
Ye s
No
No
Ye s
Open Source 2
(Energize K1)
TDN timer times out
(If Option 32A is enabled)
Close Source 1
(Energize K1)
Source 1 is powering the load
TDEC timer times out
Remove "Engine Start" signal
(De-energize Gen Start relay)
TPRE timer times out
(If Source 1 is Available)
TPRE timer times out
APPENDIX B: OPERATIONAL
FLOWCHARTS
Utility - Generator Transfer Switch
Dual Utility Transfer Switch
In-phase Transition Implementation

Other manuals for Eaton Cutler-Hammer ATC-300