Instal lation & Owner's Manual
NO TE
6 . 4.1 Location
The ooring beneath the water heater must be able
Located indoors (such as a basement or garage) and in a
vertical position. Sheltered from freezing temperatures.
Provisions made to shelter the area from water damage.
Metal drain pan installed and piped to an adequate drain.
Su
t room to service the water heater.
Su
t air for the heat pump to function,
the water heater must be located in a space >15m³, and
must have unrestricted
w.
For optimal e ncy and serviceability, the following clearances
should be maintained: 800mm on the air inlet side, 800mm on the
air outlet side, 600mm in the back, and 600mm in the front.
6.4 Installation Checklist
6.3 Electric Leakage Protector
Fig. 6-3
L
N
GND
Power Cable
RCD
The unit cannot be placed into any type of closet or small
enclosure.
The site location must be free from any corrosive elements
in the atmosphere such as sulfur,
uorine, and chlorine.
These elements are found in aerosol sprays, detergents,
bleaches, cleaning solvents, air fresheners, paint, and
6. 4.4 Electrical Connections
6.4.2 Water System Piping
PRT(Temperature and pressure relief valve) properly
installed with a discharge pipe run to an adequate drain
and sheltered from freezing.
All piping properly installed and free of leaks.
Tempering valve installed per manufacturer’s instructions.
6.4.3 Condensate Drain Line Installation
Must be located with access to an adequate drain or
condensate pump.
Condensate drain lines installed and piped to an adequate
drain or condensate pump.
The water heater requires 230 VAC for proper operation.
Wiring size and connections comply with all local applicable
codes and the requirements of this manual.
Water heater and electrical supply are properly grounded.
Correctly sized overload fuse or circuit breaker protection
installed.
6.4.5 Post Installation Review
Understand how to use the User Interface Module to set the
various modes and
functions.
Understand the importance of routine inspection/maintenance
of the condensate drain pan and lines. This is to help
prevent any possible drain line blockage resulting in the
IMPORTANT: Water coming from the plastic shroud is an
indicator that both condensation drain lines may be blocked.
Immediate action is required.
To maintain optimal operation check, remove and clean the
varnish removers, refrigerants, and many other
commercial and household products. In addition excessive
frequent cleaning.
The ambient air temperature must be above -7ºC and
below 43ºC . If the ambient air temperature falls outside
these upper and lower limits the electrical elements will be
activated to meet the hot water demand.