2.02 ELECTRIC MOTOR
2.02.01 ELECTRICAL CONNECTIONS
THE USER SYSTEM AND THE RESPECTIVE CONNECTIONS MUST BE MADE IN
STRICT OBSERVANCE OF THE REGULATIONS IN FORCE, BY COMPETENT
PERSONNEL QUALIFIED TO DO THE JOB.
BEFORE CONNECTING THE APPLIANCE BY MEANS OF THE PLUG SOCKETS,
TURN THE MAIN SWITCH TO OPEN POSITION "O".
2.02.02 COMMISSIONING
These machines do not need any adjustment or particular precautions before
commissioning.
The only controls to perform concern:
- Machine integrity:
make sure that nothing happened during transport that could damage the insulation or
mechanical parts.
- Completeness of supply:
check that all the supplied accessories are fitted.
- Oil level:
check the oil level and top up if necessary as per the instructions in Para 3.01.
IMPORTANT: Before loosening the oil cap carefully read the instructions in Para
3.01.
2.03 DOUBLE-ACTING LEVER
The double-acting lever has two positions (see fig. 2)
- Position 1 ( open ): The piston returns to its original position.
- Position 2 ( close ): The piston performs its outward stroke (bending-straightening
phase).
Fig. 2