Quick Start Guide
9
September 2017
2. Units with flanged process connections:
a. Install the flanges in the process pipe. The distance between flanges
should be equal to the overall length of the flowmeter, plus clearance for
gaskets.
b. Install the unit between the flanges, using studs, nuts, and gaskets
appropriate for the flange size/rating and process conditions. Proper
support is needed at the flange connections as shown below.
See Figure 11.
3. Units with threaded process connections:
a. Install the unit using the appropriate threaded connection hardware.
4. Units with Socketweld Bodies:
a. To ensure perpendicularity of the pipe to the orifice fitting, the socket
diameter is smaller than the standard pipe OD. The pipe OD must be
machined-to-fit prior to welding.
b. To prevent damage, remove the transmitter prior to welding.
Figure 11. Recommended Support Locations for Installation
A. Support
B. No step
5. Once the Rosemount 1195 is installed ensure that it is supported properly
and take precautions to ensure that it is not used as a step. Refer to Figure 11
for support locations.
AA
B
00825-0100-4686 FA.fm Page 9 Thursday, September 21, 2017 10:45 AM