Examples Resuming commissioning
5.3 Resuming commissioning
Continue heating system commissioning
Continue to commission the heating system and
perform a function test of components such as pumps,
mixing valves, temperature sensors, etc.
Next, make customer-specific adjustments to the
control system such as hot water temperatures, buffer
charging time slots, heating time slots and room tem-
peratures...
The required parameters are listed in Chapter 6 "
Con-
figuration parameter".
Making a backup after commissioning
Back up the configuration straight away after you have
adapted the heating system to suit the customer's re-
quirements. See Chapter 4 "
Backing up and restoring
a configuration".