Page 10
November, 2003
402 Operator And
455 D Control Panel Installation Manual
1
5
3
6
8
2
4
9
7
3
5
1
A
A
B
A
B
C
C
D
A
Figure 7. The layout of a sample gate system
Locate switches at least
10 ft from the gate
1 Operator
Wire Gauges for Given Voltage
2 Control Panel
220 VAC 115 VAC
3 Photocell A 2 × 18 AWG A 2 × 18 AWG
4 Switch B 4 × 14 AWG B 4 × 14 AWG
5 Junction box (see text) C 5 × 18 AWG C 5 × 18 AWG
6 Reversing edges D 4 × 14 AWG up to 414 ft D 3 × 14 AWG up to 130 ft
7 Gate stops
3 × 10 AWG up to 340 ft
8 Switch
9 Wiring to main circuit breaker