Service Policy Continued
Start-Up Record
1. All anchor bolts tightened to specications.
2. All pipe couplings tightened to specications.
3. Inlet pressure switch (if applicable) installed.
4. System pipes are clean and upstream ltration in place.
5. System leak checked and all air vented from system.
6. ALL safety devices in place.
Installation and Start-up Information
Start-up Date: _________________________ Model #: _______________________________
Serial #: ______________________________ Installation Date: _________________________
Installed By: ___________________________
Operating Conditions
Pump Inlet Pressure: ______________ Turbine Inlet Pressure: ______________
Pump Outlet Pressure: ______________ Turbine Outlet Pressure: ______________
Pump Flow: ______________ Turbine (Brine) Flow: ______________
Bypass Flow Rate: ______________ (If equipped)
Aux Valve Position:
OPEN
PARTIAL
CLOSED
Pipe Connection(s)
Victaulic connection
Flanged connection: Flange Pipe Size (Inlet) __________, Gap __________
Flange Pipe Size (Discharge) __________, Gap __________
General Notes:
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
This report has been lled out by: __________________________________Date: ___________