Specications Continued
Maintenance Schedule
By following the schedule of preventive maintenance presented below, the MSD pump will deliver
years of trouble-free performance.
One (1) day after commissioning
8. Recheck pump alignment (refer to Final Pump Alignment).
9. Visually inspect exible coupling and tighten the coupling bolts to the specied torque as nec-
essary.
10. Fill out and submit all warranty documentation to FEDCO.
Six (6) months after commissioning
1. Inspect pump alignment (refer to Final Pump Alignment).
2. Inspect exible coupling: check for wear, irregularities, torsional backlash, running behavior
and tightening torque (refer to Flexible Coupling Check).
3. Inspect for leaks, damaged gaskets and condition of all pipe couplings.
4. Wipe pump, motor and baseplate with a clean, damp cloth.
Annually
1. Inspect pump alignment (refer to Final Pump Alignment).
2. Inspect exible coupling: check for wear, irregularities, torsional backlash, running behavior
and tightening torque (refer to Flexible Coupling Check).
3. Inspect mechanical seal for early signs of leakage or failure.
4. Inspect balance disc (refer to Balance Disc Specications).
NOTES: If balance disc requires replacement, the mechanical seal should also be replaced.
5. Inspect drain line, and clean any build up.
6. Inspect for leaks, damaged gaskets and condition of all pipe couplings.
7. Wipe pump, motor and baseplate with a clean, damp cloth.