27
STEP 7
\
DC ONLY: SLIDE BATTERY TRAYS OVER THE BALL SCREW TUBE WITH
THE WIDE OVERHANG SIDE OF THE TRAY TO THE OUTSIDE OF THE
LIFT TO PROVIDE MORE CLEARANCE. PLACE FIRST BATTERY TRAY 8
INCHES FROM CORNER POST AND SECOND BATTERY TRAY 3
INCHES FROM FIRST TRAY (SEE VSD DRIVE INSTRUCTIONS). FASTEN
WITH (4) 3/8” x 5 ½” BOLTS WITH (4) 3/8” NYLOCK NUTS (FIGURE
7.7). TORQUE COMPLETELY ONCE WIRING IS DONE AFTER WIRING IS
COMPLETE.
PLACE BATTERIES AND BATTERY BOXES INTO TRAYS (FIGURE 7.8)