Operating Manual 51
Starting up and operation
Indicators on the control panel
Power-on indicator (three colors)
Lights up green when the server is switched ON.
Lights up orange when the server is switched OFF, but mains
voltage is present (standby mode).
I After connecting the server to the mains, it will take about
60 seconds until the server will switch into standby mode.
Flashes light-green / orange: iRMC booting
I After linking the server to the mains voltage (system unit
is switched on / after mains failure) the iRMC will boot.
The system cannot be switched on, until the iRMC boot
sequence is complete. During this time, the power-on
indicator will flash light-green / orange.
Lights up light-green: power-on delay
I After shutting down, the server cannot be switched on
again right away. If the On/Off button is pressed right
after shutting down the server, the power-on indicator will
light up light-green until the delay period ends and the
server will boot.
If line voltage is insufficient, the server cannot be
switched on. If the On/Off button is pressed in this state,
the power-on indicator will light up light-green.