EasyManua.ls Logo

GE AV-Line - Field Connections, Testing, and Operation; Ground-Fault Protection Systems; Fuse Selection and System Testing

GE AV-Line
12 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Installing
The
AV
-
Line
Switchboard
3
-
PHASE
4
WIRE
SUPPLY
N
G
.
V
1
2
3
©
L
©
SERVICE
ENTRANCE
MAIN
BREAKER
)
)
)
FIELD
CONNECTIONS
AND
TESTING
OF
GROUND
-
FAULT
PROTECTION
SYSTEMS
(
7
)
In
the
service
-
entrance
section
,
the
neutral
conductor
shall
be
bonded
to
the
switchboard
ground
bus
by
a
main
bonding
jumper
(
ground
strap
)
(
NEC
250
-
5
;
UL
-
891
,
Para
.
23.8
and
23.12
)
.
This
grounding
point
on
the
neutral
conductor
shall
be
located
on
the
supply
side
of
any
ground
-
fault
sensors
in
-
volving
the
neutral
conductor
(
UL
-
891
,
Para
.
15.4
and
15.5
)
.
Grounding
connections
shall
not
be
made
to
the
neutral
con
-
ductor
on
the
load
side
of
the
service
disconnecting
means
(
NEC
250
-
23
a
;
UL
-
891
,
Para
.
15.4
)
.
(
?
)
On
load
feeders
,
run
all
phase
conductors
(
and
neutral
if
used
)
through
the
sensor
window
(
s
)
,
with
all
in
the
same
direction
with
respect
to
sensor
polarity
.
(
J
)
Do
not
run
equipment
ground
conductors
through
ground
-
fault
sensors
.
Connect
them
directly
to
the
switchboard
ground
bus
(
not
to
the
neutral
bus
)
(
UL
-
891
,
Para
.
38.39
)
.
(
71
)
Connect
the
service
grounding
electrode
(
water
pipe
,
etc
.
)
to
the
lug
provided
on
the
switchboard
ground
bus
for
this
pur
-
pose
(
NEC
250
-
26
c
;
UL
-
891
,
Para
.
23.6
)
.
(
J
)
Whenever
a
service
is
derived
from
a
grounded
neutral
sup
-
ply
,
the
grounded
neutral
conductor
must
be
brought
into
the
service
-
entrance
equipment
,
even
if
the
grounded
conductor
is
not
needed
for
the
load
supplied
by
the
service
(
NEC
250
-
23
b
)
.
This
is
required
to
provide
a
low
-
impedance
ground
-
fault
current
return
path
to
the
neutral
to
assure
operation
of
the
overcurrent
device
,
for
safety
to
personnel
and
property
.
(
&
)
Refer
to
GEI
-
48907
for
instructions
for
conducting
perfor
-
mance
tests
of
new
installations
of
ground
-
fault
protection
systems
,
as
required
by
NEC
230
-
95
(
c
)
.
4
WIRE
IGF
NEUTRAL
-
1
N
«
-
N
aus
-
o
-
&
;
T
)
)
)
)
)
)
FDR
¥
1
FDR
#
2
iE
-
yi
IGF
=
INTEGRAL
GROUND
FAULT
PROTECTION
3
WIRE
IGF
GHD
^
rr
8
US
©
y
V
'
'
t
1
2
3
'
'
©
'
i
'
V
V
2
3
.
N
vj
.
©
v
V
I
I
I
I
I
I
I
I
I
1
I
2
3
I
I
I
1
N
G
J
I
2
3
G
|
3
PHASE
3
WIRELOAD
~
~
|
|
3
-
PHASE
4
WIRE
LOAD
|
TYPICAL
SINGLE
-
SOURCE
GROUND
FAULT
PROTECTION
USING
INTEGRAL
GROUND
FAULT
TRIPS
FIGURE
13
FUSE
SELECTION
The
proper
fuses
for
each
circuit
should
be
selected
based
on
load
characteristics
(
see
Ambient
Temperatures
and
Circuit
Loading
)
and
available
short
-
circuit
current
at
the
line
terminals
of
the
switchboard
.
Select
a
fuse
for
which
the
rating
of
the
combination
fuse
and
switch
equals
or
exceeds
the
available
short
-
circuit
current
.
Removable
link
-
type
fuses
are
not
recommended
.
TESTING
AND
INSPECTION
After
the
equipment
has
been
installed
and
all
connections
made
,
it
should
be
tested
and
inspected
BEFORE
ENERGIZING
.
Although
the
equipment
and
devices
have
been
inspected
at
the
factory
,
a
final
field
test
should
be
made
to
be
certain
that
the
equipment
has
been
properly
installed
and
that
all
connections
are
correct
and
have
not
become
loose
in
transportation
.
It
is
recommended
that
the
switchboard
be
completely
wire
checked
,
and
all
bolts
and
terminals
double
checked
for
tightness
.
Check
all
Kirk
key
interlocking
schemes
to
insure
desired
performance
.
The
incoming
line
should
be
completely
de
-
energized
while
the
tests
are
in
progress
.
In
addition
to
these
mechanical
checks
the
switchboard
should
be
meggered
.
Meggering
should
be
performed
with
all
switchboard
devices
in
the
open
position
and
all
instrumentation
and
control
fuses
removed
.
A
megger
(
megohmmeter
)
developing
500
volts
should
be
used
.
As
a
guide
switchboards
tested
when
leaving
the
factory
have
shown
typical
minimum
values
of
100
megohms
.
Any
switchboards
job
tested
under
the
above
conditions
showing
values
considerably
below
this
should
be
inspected
for
possible
tracking
on
insulation
or
insulation
breakdown
.
All
scraps
of
wire
,
plaster
,
dust
and
other
foreign
material
must
be
removed
.
Vacuum
cleaning
is
the
recommended
method
of
removal
.
After
thorough
cleaning
and
inspection
,
if
the
megger
reading
is
still
low
,
it
may
still
be
safe
to
energize
the
equipment
.
When
restoring
flooded
or
wet
equipment
to
service
,
for
example
,
it
is
accepted
maintenance
prac
-
tice
to
require
a
minimum
of
one
megohm
before
energizing
.
Under
damp
or
humid
conditions
it
is
considered
good
practice
to
operate
the
equipment
at
lower
-
than
-
rated
voltage
for
a
short
time
,
if
possible
,
to
improve
the
low
megger
reading
.
Instructions
for
inspection
and
testing
of
low
voltage
power
circuit
\
breakers
are
given
in
the
applicable
individual
instruction
book
.
Direc
-
tions
for
testing
devices
such
as
relays
,
instruments
and
meters
are
given
in
the
instruction
book
furnished
for
each
device
.
Protective
relays
must
be
coordinated
with
other
relays
in
the
system
,
therefore
these
relays
are
to
be
set
by
the
purchaser
.
General
instructions
on
setting
the
relays
are
given
in
the
relay
instruction
books
.
3
-
PHASE
4
WIRE
SUPPLY
1
2
3
N
G
ALTERNATE
SENSOR
ARRANGEMENTS
I
t
2
3
N
I
ALTERNATE
SENSORS
FOR
MAIN
BREAKER
GFP
c
X
>
t
©
I
ZERO
SEQUENCE
GROUND
RETURN
SENSOR
)
)
SERVICE
ENTRANCE
MAIN
BREAKER
12
3
N
GFR
I
x
>
-
(
(
I
I
ZERO
-
SEQUENCE
OR
RESIDUAL
SENSOR
RESIDUAL
2
3
N
NEUTRAL
N
BUS
(
X X X
^
I
RESIDUAL
1
!
>
~
Epl
)
)
>
-
-
)
)
)
GFR
-
GROUND
FAULT
RELAY
FDR
01
GFR
FDR
02
GRD
c
sus
©
'
'
'
'
\
'
>
t
\
r
1
2
3
N
1
2
3
i
i
:
r
I
i
i
©
©
L
1
1
1
1
2
3
N
G
I
I
I
I
I
1
2
3
G
I
I
I
I
|
3
PHASE
4
WIRE
LQAD
~
~
|
|
3
PHASE
3
WIRE
LOAD
|
TYPICAL
SINGLE
-
SOURCE
GROUND
FAULT
PROTECTION
USING
GROUND
FAULT
RELAYS
FIGURE
12
10
Courtesy of NationalSwitchgear.com

Related product manuals