3. Receiving the product
3.1 Performance test
The pumps are tested 100 % before leaving the
factory. The test includes a function test where the
pump performance is measured to ensure that the
pump meets the requirements of relevant standards.
Test certificates are available from Grundfos.
3.2 Transporting the product
WARNING
Overhead load
Death or serious personal injury
Pay attention to the pump weight, and
take precautions to prevent personal
injury if the pump topples or falls by
accident.
Always transport the pump in the specified
position.
Securely fasten the pump to prevent damage to
the shaft and shaft seal caused by excessive
vibrations and knocks.
Do not lift the pump by the shaft.
3.3 Inspecting the product
Confirm that the product received is in accordance
with the order.
Confirm that the voltage, phase and frequency of
the product match the voltage, phase and
frequency of the installation site. See
Identification.
Check the product for defects or damages
immediately upon receipt. Any accessory ordered
will be packed in a separate container and
shipped with the product.
If any equipment is damaged in transit, report it
immediately to the carrier's agent. Make complete
notations on the freight bill.
3.4
Storage after delivery
The contractor must inspect the equipment on
delivery and make sure it is stored so as to avoid
corrosion or damage. See Storing the product.
Related information
8. Storing the product
4. Installing the product
4.1 Mounting of motor on bare shaft pumps
4.1.1 Mounting of motor on pump housing without
feet
The pumps are supplied with a transport bracket
protecting the shaft seal during transport. When you
mount the motor, follow the instructions and drawings
as below.
1. Remove the coupling guard and loosen the set
screws in the shaft.
TM053327
2. Place the pump on the motor.
TM033906